What We Do

On-grid Access

As of July 2025, the cumulative connectivity rate in Rwanda is 84.6% of Rwandan households whereby 59.6% of all households in Rwanda are connected to the national grid. The number of on-grid connections has grown more than 12 times over the last 20 years.

Overview

As of July 2025, the cumulative connectivity rate in Rwanda is 84.6% of Rwandan households whereby 59.6% of all households in Rwanda are connected to the national grid. The number of on-grid connections has grown more than 12 times over the last 20 years.

District

On-grid

Bugesera

54.7%

Burera

70.7%

Gakenke

49.6%

Gasabo

87.2%

Gatsibo

37.3%

Gicumbi

51.9%

Gisagara

44.2%

Huye

49.8%

Kamonyi

48.3%

Karongi

51.1%

Kayonza

46.1%

Kicukiro

90.9%

Kirehe

46.7%

Muhanga

62.5%

Musanze

68.5%

Ngoma

45.5%

Ngororero

53.7%

Nyabihu

57.9%

Nyagatare

46.1%

Nyamagabe

38.7%

Nyamasheke

71.1%

Nyanza

38.7%

Nyarugenge

90.6%

Nyaruguru

49.3%

Rubavu

75.7%

Ruhango

58.2%

Rulindo

47.7%

Rusizi

75.7%

Rutsiro

58.7%

Rwamagana

60.2%

NATIONAL

59.6%

Project List

Access by District

Reporting period: July 2025

Bugesera54.7%
Burera70.7%
Gakenke49.6%
Gasabo87.2%
Gatsibo37.3%
Gicumbi51.9%
Gisagara44.2%
Huye49.8%
Kamonyi48.3%
Karongi51.1%
Kayonza46.1%
Kicukiro90.9%
Kirehe46.7%
Muhanga62.5%
Musanze68.5%
Ngoma45.5%
Ngororero53.7%
Nyabihu57.9%
Nyagatare46.1%
Nyamagabe38.7%
Nyamasheke71.1%
Nyanza38.7%
Nyarugenge90.6%
Nyaruguru49.3%
Rubavu75.7%
Ruhango58.2%
Rulindo47.7%
Rusizi75.7%
Rutsiro58.7%
Rwamagana60.2%

Related Projects

Methane gas

Kibuye Power 1

pilot project located in Karongi district, has been generating around 3MW of electrical power with the design capacity of 3.6 MW; In 2016 Symbion Power acquired the KP1 barge and onshore facility.Symbion through the liquidation process and is now mobilizing funds to revive the plant and scale it up to 25 MW.

View project

Methane gas

KivuWatt Project Phase I

A subsidiary of Contour Global (US-based Company) entered into commercial operations since 31st December 2015 and operates at base load with a nominal gross capacity of 26 MW.

View project

Related News