Overview
Rwanda may have geothermal potential which is manifested in the form of hot springs (Fig. 1) and hosts two prospective zones for geothermal energy exploration: the first zone in the north-western region (Gisenyi, Karisimbi, and Kinigi) which is associated with volcanoes and the second zone in the southern region (Bugarama) associated with faults in the East African Rift (Fig. 2). Three main prospect areas have been demarcated for further exploration: Kinigi, Gisenyi and Bugarama. The potential of geothermal energy is still uncertain.

Fig 1: Bugarama hot springs
Fig 2: Geothermal potential areas
Overview of Geothermal Development
Serious investigations on Rwanda geothermal resources started in 2006 with a view of diversifying energy sources for electricity generation. Surface geo-scientific studies conducted from 2006 to 2012 indicated that Rwanda has four potential geothermal prospects namely; Karisimbi, Kinigi, Gisenyi and Bugarama. After detailed surface investigations in Karisimbi, two deep exploration wells were drilled with the aim of confirming the existence of the resource. Unfortunately, subsurface geological formation and well testing indicated no evidence of a geothermal system in the Karisimbi drilling area.
Following Karisimbi unfortunate results, a geothermal master plan was developed in 2015. The geothermal master plan provides potential estimates for each geothermal prospect area and gives a clear plan of priorities for the exploration of potential geothermal sites in the country. The potential was estimated at a maximum 100 MW for the country.
Additional surface studies have been conducted in Kinigi prospect and the results from these studies ranked Kinigi as a risky area for geothermal resources exploration.
The new strategy for geothermal exploration suggests for each prospect 5 years of geothermal resources exploration including surface investigations, exploration drilling and well testing followed by 3 years for the construction power plant only if the resource is proven.
The current plan for geothermal exploration is to conduct additional studies in Bugarama and Gisenyi prospects.
Current ongoing activities
Detailed surface investigations have been carried out in Kinigi, Gisenyi and Bugarama prospects and the expected outcome is an update of the conceptual model of the geothermal system in each potential prospect to decide for subsurface exploration.
| Geothermal prospect | Reconnaissance Study | Additional detailed Survey | Gradient Wells | Exploration Wells |
| Gisenyi | Done | Ongoing | FS | FS |
| Bugarama | Done | Ongoing | Done | FS |
(FS: For Schedule)
Given the complexity involved in determining the commercial viability of geothermal power, the Government of Rwanda is committed to reducing risks associated with geothermal exploration by drilling exploration wells to prove the existence of the resource.
Furthermore, Rwanda will host the Seventh Africa Rift Geothermal Conference (ARGeo-C7) in October 2018. The theme of ARGeo-C7 is “Geothermal: Solution to Africa’s Energy needs”. This conference is expected to attract over 400 local, regional and international experts, policy makers, developers and financiers from all over the world.
Project List
Related Projects
110 kV Single Circuit: Mukungwa-Nyabihu
The project consists of construction of 29km long transmission line linking Mukungwa to Nyabihu
View projectKibuye Power 1
pilot project located in Karongi district, has been generating around 3MW of electrical power with the design capacity of 3.6 MW; In 2016 Symbion Power acquired the KP1 barge and onshore facility.Symbion through the liquidation process and is now mobilizing funds to revive the plant and scale it up to 25 MW.
View projectKigali Network Strenghening 1 - 2
Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 6 identified substations )
View project220 KV Bwishyura-Kigoma-Rwabusoro
The project consists of building a 62 km long 220KV transmission line linking Bwishyura, Kigoma and Rwabusoro.
View projectKivuWatt Project Phase I
A subsidiary of Contour Global (US-based Company) entered into commercial operations since 31st December 2015 and operates at base load with a nominal gross capacity of 26 MW.
View projectKigali Network Strenghening 1 - 3
Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 11 identified substations )
View project