Overview
REF Window 5
In a move to increase Solar Home System (SHS) installations and electrification of households in rural areas of Rwanda, the Renewable Energy Fund (REF) and Rwanda Energy Access and Quality Improvement Project (EAQIP) off-grid component 3a implemented by the Development Bank of Rwanda Plc. have launched a Results-based Financing (RBF) subsidy called “RBF Window 5”.
The Subsidy is designed to address the affordability of SHS faced by rural households through the reduction of prices for the systems at varying amounts allocated to Ubudehe 1, 2, and 3 categories with the aim of reaching the lowest income population in Rwanda.
The FRW 29.24 billion (US$ 30 million) subsidy window is funded by the World Bank and is expected to trigger at least 370,000 off-grid connections. It is expected that this RBF facility will boost uptake of REF funds thus enabling the project to connect Rwandan households using off-grid solutions. The subsidy will be channeled through eligible Off-grid Solar Companies (OSCs) that have signed a Memorandum of Understanding with EDCL and the supplied SHSs must be meeting the Ministerial Guidelines on Minimum Standards Requirements for Solar Home Systems that was published in June 2019.
Click the links below for: |
Related Projects
110 kV Gasogi-KSEZ
The project consists of building a 2.2km long 110KV transmission line linking Gasogi substation to Kigali Special Economic Zone
View projectShema Power Lake Kivu
Shema Power Lake Kivu Limited (SPLK ltd) signed a 25-year power purchase agreement (PPA) with the Rwanda Energy Group (REG) for a 56 MW net power output from methane gas. The Power plant will be located on Nyamyumba sector in Rubavu District. The first barge will provide 14 MW of electricity 15 months after the project reaches Financial Close.
View projectKigali Network Strenghening 1 - 1
Improved stability of power supply in Bugesera and parts of Kigali by replacing a10MVA transformer by a 20MVA at Mont Kigali substation
View project110 kV Single Circuit: Mukungwa-Nyabihu
The project consists of construction of 29km long transmission line linking Mukungwa to Nyabihu
View projectKibuye Power 1
pilot project located in Karongi district, has been generating around 3MW of electrical power with the design capacity of 3.6 MW; In 2016 Symbion Power acquired the KP1 barge and onshore facility.Symbion through the liquidation process and is now mobilizing funds to revive the plant and scale it up to 25 MW.
View projectKigali Network Strenghening 1 - 2
Kigali distribution network reinforced (upgrade, rehabilitation and integration to SCADA of 6 identified substations )
View project